Domar almost finished
Project update van 3 augustus 2021 door Surendra Nath Singh
Although the lockdown in Bangladesh is causing a delay on the construcion of both buildings, the people in Domar have been working very hard to finalize the building as far as possible.
The construction work for Domar association is on final stage, wall and roof construction with wall plaster has been done. Mason is waiting for availability of door and windows, when it will available mason will fit them and start for finishing task. Continues lockdown making delay to finish work in time. The building construction work for Tetulia association is in under implementation process such as selecting mason, arranging materials and starting activities. Tetulia association building could be started in 2nd or 3rd week of August 2021 and expecting to complete within November 2021.