Progress at Kalumamba
Project update van 28 september 2018 door Mussa Nyirenda
After the team MA218 left, the local community focused on the work to be done for the MA418 project team, so not much work has been done on the first project.
At one house the brick laying work is finished, and the painting was being done, so this house is already occupied by 1 teacher.
The other house needs plastering and finishing too.
For the classrooms: the plastering and flooring has been done in 1 classroom, and the other classroom and the office only plastering. So the flooring work is remaining there as well as some other finishing tasks.
Mussa agreed with the community to have all the work done by the end of October. So hopefully with the next update we can share more results.