Report from local coordinator Mussa

De partner vertelt... van 20 september 2016


Introduction
The objective was to construct a school block with two classrooms and an office in between including the construction of a toilet with two doors.

The construction
The school block was constructed up to roofing. Further to this beam filling was done, sketting outside and plastering part of the inside walls was also done. The toilet was constructed up to roofing.

Cooperation with the World Servants Staff.
There was very good cooperation between the staff and CCAP. There was cordial working relationship between the staff from world servants and CCAP hence a successful project.