Work progressing well and at a good pace in Liziwazi

Project update van 15 november 2019 door Mussa Nyirenda


The other classroom also plastered and flooredLatrines have a roof now and only require beam fillingInside of the classrooms plastered and flooredOverview of the schoolyard. new CRB on the left.Side view of the classroom block: also nicely plasteredTeacher house renovated by communityThe classroomblock is now plastered

The community is still very eager to work, so: they did! Read below what they've done.

The community has made a lot of progress on the school block as the only work remaining is drainage and fixing of doors and glasses. The work on teachers house is also progressing well such that the teacher has occupied it. For now what remains on the renovation of the teachers house is fixing of glasses which is waiting for the skilled glass fixer to do the work. On a different note the school started administering lessons to learners and the community is very excited that their children will now travel a short distance to school more especially those in grade 1 and 2. the enrolment is currently at 70.